What a difference a year makes!

Phase I of the bunker renovation project started Dec. 6th of last year(2012). We had very little snow fall during that winter and moderate temperatures allowed the project to progress smoothly.
This year(2013) we were able to get a jump on Phase II with a start date of mid- October. With the good weather we had this fall we were able to complete the work at the following areas:

-#4 green and (2) greenside bunkers.
-#3 green and approach (removal of 2 bunkers).
-#18 fairway right side bunkers(4).
-#1 fairway (one bunker removed and fairway graded).
-Area between 1 and 18 (improved drainage with 8" pipe).
-#1 greenside bunker restoration(4 bunkers).
-#10 green and bunker work in progress.

This picture above shows that work has temporarily shut down due to the snow and below freezing temperatures. Hopefully the snow will melt and the work will continue.