Pages

Wednesday, July 10, 2013

New SHORT GAME AREA progressing!

With the bulk of the earth moving complete, the shaping of the green surface is next. After the topography of the green is roughed out and sloped properly the cavity of the green is carved out and edged. The next phase is to trench the drainage lines, install  drainage pipe and stone. When that task is complete, up to 250 tons of high sand greens construction mix will be installed in the cavity. Future postings will show those phases.

No comments:

Post a Comment